The schedule consists of the main parts of the LRR project. As a case study, an arbitrary project starting date of January 2001 is assumed. Figure 4-39 shows the fictitious schedule that relates to this case study. The dates shown below should not be considered as fixed values but serve to create the overall view.

  • The LRR Company would be initiated in January 2001
  • The participants to the first selection rounds would be registered May 2002 to April 2003
  • Qualification races and testing procedures would take place from August 2003 to April 2004
  • The spacecraft would be designed from June 2001 and would take 2.5 years.
  • The race would take place in July 2004.
  • The schedule does not show the LRR Company's activities after the LRR.